We are adding an 18'x 45' one room addition to this home in Burlington.
Save this site to your favorites to monitor our progress and see new projects as they start. |
click on image
|
We are now prepairing to pour a concrete slab. |
The next step here is that all footings are dug 4' below grade and our slab form is set up and poured. |
click on image
|
click on image |
Our slab foundation has been poured all at once. That is our footings and slab is all one piece.
|
We have built a pressure treated 2"x 6" knee wall and have our subfloor almost completed. |
click on image
|
click on image
|
It has been about three days now and we are almost done with the walls.
|
Now two weeks have passed and we are ready to install the siding.
|